Skip links

31-32 Soho Square

We are here to answer any question you may have.

31-32 Soho Square

31-32 Soho Square (aka Twentieth Century House) is a notable 1930s building with a deep-rooted history in London’s original film–making district.

The former HQ of Twentieth Century Fox sat vacant and, while scripts were being written for its new role, General Demolition was greenlit to undertake enabling works behind its neo-Georgian façade.

Professional Team:

Royal London UK / RE Fund Rougemount

Programme duration:

13 weeks

Value:

Up to £750k

In Summary

Photographic condition, asbestos and building services survey

Tag and trace

Isolation of services

Installation of temporary supplies incl. wireless fire alarm system

Asbestos removal

Strip out across 8 storeys (basement, ground and 6 upper floors

Removal of no.2 lifts

Demolition of blockwork partitions

Removal of screed

Clearance of arisings

Working all the angles

The distinctive late-1930s building on the South East corner of Soho Square required strip works to all floors, asbestos removal and the internal demolition of blockwork partitions. General Demolition spent thirteen weeks on location and had to contend with a few changes to its call sheet before wrapping a little later than planned.

The project

It is not every day that a strip out includes the removal of not one but two in-house screening rooms... we should have expected nothing less from Twentieth Century House!

Situated on the ground floor of this 6947sqm building, these large theatres were removed alongside other spaces more typical of a Class B1 office building.

Adopting a top-down approach to the strip out, the team worked methodically through the building. A faulty lift meant slower-motion for a brief period and the surprise discovery of a secondary celling made for a thriller on set.

Quiet Please

With a sound recording studio immediately adjacent, noise was always going to be an issue. General Demolition’s well tested neighbour liaison programme was put into action early on.

A good flow of communication meant that the team was able to respond quickly to noise issues – downing tools and adapting its working hours – to mitigate the impact on surrounding businesses.

Never ones to make a scene, the unavoidable knock-on effect to our programme was minimised through open dialogue with the client team and the hard work of GD’s A-list crew.

Explore
Drag