In summary

Strip out false ceilings, partitions, kitchenettes, associated pipework

Infilling staircases

Removal and infilling of glass staircase

Navigating logistical hurdles due to the building's location and proximity to busy areas

Maintaining live services to the sixth floor

Ensuring minimal disruption to surrounding businesses and pedestrian traffic

Maintaining security, especially in the loading bay and around the sixth floor

Management of waste and debris

Maintaining logistics and loading bay challenges for heavy installation work

The project

The refurbishment project at 6 More London will ultimately create the latest in desirable workplace environments, coupled with a comprehensive upgrade to the most stringent environmental regulations.

GD's challenge was multi-faceted: executing a comprehensive stripping and refurbishment of floors 1 to 5, while ensuring uninterrupted operations to a live client on the sixth floor - and minimal disruption to the ground floor retail spaces.

Key achievements

Maintained critical services and operations on the sixth floor and ground level.

Achieved a significant recycling rate, reusing materials where possible.

Successfully navigated the complexities of a busy urban environment.

Strengthened client relationships through efficient and considerate project execution.

SPOTLIGHT ON GD

Maintaining excellence in modern spaces

With this project, General Demolition has once again demonstrated its skill in executing complex projects in dynamic urban environments. The 6 More London refurbishment stands as a symbol of GD's dedication to precision, sustainability, and effective stakeholder collaboration. This project maintained the functionality of a modern workspace while also adapting it to meet the future trends and requirements of the evolving business world.

RE-USE RATE

20% was achieved on this project.