6 More London
Even modernist architecture needs to be modernised sometimes. 6 More London may still have the strikingly avant garde exterior, but the 2005 interior was ripe for not just renewal, but also a thorough upgrade to align with current future legislation and market needs.
This is all in a day's work for equally modern General Demolition, but the location did provide some particular challenges, with 6 More London being in the heart of a vibrant business district, with Hilton Hotel, Ernst and Young's headquarters, and Southwark Crown Court all being neighbours.
Professional Team:
SMPI Ltd / G&T / Storey Project
Programme duration:
14 weeks
Value:
Over £750k
In summary
Strip out false ceilings, partitions, kitchenettes, associated pipework
Infilling staircases
Removal and infilling of glass staircase
Navigating logistical hurdles due to the building's location and proximity to busy areas
Maintaining live services to the sixth floor
Ensuring minimal disruption to surrounding businesses and pedestrian traffic
Maintaining security, especially in the loading bay and around the sixth floor
Management of waste and debris
Maintaining logistics and loading bay challenges for heavy installation work
The project
The refurbishment project at 6 More London will ultimately create the latest in desirable workplace environments, coupled with a comprehensive upgrade to the most stringent environmental regulations.
GD's challenge was multi-faceted: executing a comprehensive stripping and refurbishment of floors 1 to 5, while ensuring uninterrupted operations to a live client on the sixth floor - and minimal disruption to the ground floor retail spaces.
Key achievements
Maintained critical services and operations on the sixth floor and ground level.
Achieved a significant recycling rate, reusing materials where possible.
Successfully navigated the complexities of a busy urban environment.
Strengthened client relationships through efficient and considerate project execution.
SPOTLIGHT ON GD
Maintaining excellence in modern spaces
With this project, General Demolition has once again demonstrated its skill in executing complex projects in dynamic urban environments. The 6 More London refurbishment stands as a symbol of GD's dedication to precision, sustainability, and effective stakeholder collaboration. This project maintained the functionality of a modern workspace while also adapting it to meet the future trends and requirements of the evolving business world.
RE-USE RATE
20% was achieved on this project.